DPFMEA.comDaniel Czarkowski

Key projects

Noble Voyager — Ring Bus Upgrade, ABS EHS-E NotationMilestone

Noble Corporation — first in Noble's fleet

Ring bus upgrade with ABB EPPS protection system. DP FMEA with DPSI (DP System Integration), OCIMF statement of compliance, DP FMEA proving trials with findings close out, and MTS gap analysis.

“This is a significant accomplishment and, notably, a first for Noble's fleet. This milestone reflects an extraordinary level of commitment, technical expertise, collaboration, and perseverance across multiple teams and organizations. […] When we successfully complete this final phase, the NVOY Closed Bus Upgrade Project will likely represent the first drillship in the world to meet the intent of the MTS and Shell LIFE+ guidance, which serves as the basis for much of the DNV and ABS rulemaking.”
— Internal recognition note, Noble Corporation leadership

Conversion of Motor Tankers to FSO

Banyu Urip Project — Mobil Cepu Ltd. & Sembawang Shipyard, Singapore

Paladin DesignBase / Power Analytics EDSA modelling of single line diagram, voltage drop calculation, short circuit calculations, transient stability study, motor starting report, load schedule, cable trays, arrangements, earthing philosophy.

FEED Seismic Vessel

Leading engineer for design in Intergraph SmartPlant Electrical

Conversion of Aframax Tankers into Modular Capture Vessel

American Eagle Tankers

Single line diagram, block diagrams, load schedule, cable trays, arrangements, switchboard estimation, variable speed drives, telecom philosophy, cable schedule.

FEED FPSO Ichthys

Subcontractor for Aker Solutions, Kristiansand (Norway)

Single line diagram, block diagrams, load schedule, cable trays, arrangements, switchboard estimation (ABB MNS), MCC, UPS (Chloride, Gutor), variable speed drives (ABB ACS6000, ACS800, Rockwell, Vacon), turret philosophy, ESD & black start philosophy, HVAC input, ICSS, field instrumentation, telecom, main equipment list, P&ID review.

Pre-FEED Floating LNG (Cash field)

PTTEP Australasia Pty Ltd.

Single line diagram, block diagrams, power balance, electrical philosophy.

Pre-FEED FPSO Jordbaer (Strawberry)

BG Group

Maritime warranty services

AGIP KCO (IBEEV), National Oilwell Varco (Alfa Star project)

Issuance of certificates of approval.

Leading engineer, Passenger vessel

Cost Time Resources

Drawing list, single line diagram, line diagrams, power balance, block diagrams, PAGA/PABX, CCTV, lighting layout and calculations, arrangements.